| DATES | ACTIVITIES |
|---|---|
| Oct 30-Nov 1 | HRC and WFC alignment verification |
| Nov 2-5 | POL0V and POL60V flat fields at nominal and +/- 1 steps, FLASH SMS JGCH35A and JGCW35A on MEB Sides 1 and 2 |
| Nov 6 | External full-field WFC F606W flats at nominal and +/-1 filter wheel steps, unsuccessful target acquisition, internal HRC and WFC baseline flats |
| Nov 7 | Successful target acquisition and light leak test with proper vent configuration |