While ACS is at Goddard Space Flight Center (GSFC) during its first visit, we will have several opportunities to obtain vital calibration data. These include :
The calibrations planned for the TV run have been planned in detail. In the following, we outline our plans for the remaining ground-calibration time at GSFC.
The alignment and calibration data will be obtained in the GSFC clean room. ACS will be housed in a dark box which will be purged with dry N2(at least for portions of the tests). For the alignment portion RAS/CAL will be the stimulus. For the remaining designated calibration time, STUFF and RAS/CAL will be the stimuli. RAS/CAL will be fed by a variety of sources, including a HeNe Laser, a D2 lamp, and (if we are lucky) a monochromator. The detectors that will be tested are the High Resolution Camera (HRC#2), the Solar Blind Channel (SBC), and the Wide Field Camera (WFC#2). The last of these will not be available until January 1999.
The goals of the tests include :
for SBC and HRC.In general flat-fielding will not be the emphasis of these tests, although we will be testing the capabilities of STUFF for obtaining uniform flatfield illumination. This is because, problems with the knife-edge mask in front of the HRC and WFC detectors render pointless the task of obtaining final ground flats with these detectors. High S/N flats will be obtained for the SBC during the TV campaign.
Because of the ever-present threat (and opportunity) of schedule changes, we have planned the calibration tests to be modular, and prioritized to insure that the most important tests are the ones that get done if the duration is cut. The above goals are listed roughly in order of priority.
The following is a list of specific calibration items that will be addressed with these tests. They are arranged in rough priority order.
| ID | Title | Channels | Stimulus | Source | Purge | Goals | Notes |
|---|---|---|---|---|---|---|---|
| A | STUFF shakedown | SBC (HRC?) | STUFF | PtNe1,2, Xe, Kr | Yes | 2 | lamp functionality; uniform illumination; PMT cal (HRC); pinhole splat location; background light leak check |
| B | Image quality; focus, tip/tilt | SBC, HRC, WFC | RAS/CAL | D2(SBC)HeNe | SBC | 1,4 | RH procedures: 1h, 2h GC procedures: 21s, 22s |
| C | TV calibration SMS dryruns | HRC, WFC | Internal | Tungsten | No | 1 | TV procedures: 1h, 2h, 3h, 6wh, 1w, 2w, 3w |
| D | CCD Quantum efficiency hysterises | HRC, WFC | RAS/CAL (Alt -STUFF) | D2, QTH | No | 1,3 | procedure: 23h |
| E | CCD Overfull well test | HRC, WFC | RAS/CAL (Alt -STUFF) | D2, QTH | No | 1,3 | procedure: 24h |
| F | SBC out of band rejection | SBC, HRC | RAS/CAL | Monochromator | No | 4 | |
| G | Ramp-filter throughput vs. ![]() |
HRC, WFC | RAS/CAL | Monochromator | No | 5,6 | If no monochromator, determine filter offset spacing to use in later tests. |
| H | Throughput vs.
(most filters) |
HRC, SBC, WFC | RAS/CAL | Monochromator | SBC | 4,6 | Red leak of blue filters if no monochromator |
| I | Scattered light test Ghost image search | HRC, WFC | RAS/CAL | D2 | SBC | 3,4,7 | |
| J | Illumination angle test | HRC, SBC | STUFF | PtNe | SBC | 7 | TV procedure: 8s |
| K | Prism/Grism dispersion | SBC, HRC, WFC | RAS/CAL | Monochromator | SBC | 4 | |
| L | Polarimetry calibration | HRC | RAS/CAL | Monochromator + polarizing prism | No | 7 | |
| M | Shutter shading, linearity | HRC, WFC | STUFF | PtNe | No | 1,5,7 | |
| N | CCD Fringing | HRC, WFC | RAS/CAL | Monochromator | No | 7 |
Campaign : Pre-TV (December 1998)
ACS location : GSFC clean room - dark box
Stimuli : RAS/CAL, STUFF, RAS/CAL + Monochromator
| Stimulus color codes |
| Internal lamps : run anytime |
| RAS/CAL with various lamps |
| RAS/CAL with monochromator |
| STUFF |
Timeline :
| Seq. | Item | Title | Det. | Duration(approx) | Notes | Status |
|---|---|---|---|---|---|---|
| 1 | B | Image quality; focus tip/tilt | HRC | 4hr | |
|
| 2 | B | Image quality; focus tip/tilt | SBC | 6hr | ![]() |
|
| 3 | C | TV calibration SMS dry runs | HRC,WFC | 9hr | Spare time filler | ![]() |
| 4 | D | CCD Quantum efficiency hysterises | HRC | 7hr | ![]() |
|
| 5 | F | SBC out-of-band rejection | SBC, HRC | 3hr | ||
| 6 | I | Scattered light test / Ghost image search | HRC | 2hr | ![]() |
|
| 7 | A | STUFF shakedown | HRC,SBC | 3 days | ![]() |
|
| 8 | D | CCD Quantum efficiency hysterises | HRC | 7hr | If needed (I.e. not done with RAS/CAL) | ![]() |
| 9 | J | Illumination angle test | HRC (SBC) | 2hr (2 days) | SBC test contingent on HRC results | ![]() |
| 10 | M | Shutter shading, linearity | HRC | 3hr | Spare time filler | |
| 11 | B | Image quality; focus tip/tilt | HRC | 4hr | Alignment repeatability | |
| 12 | G | Ramp-filter throughput vs. ![]() |
HRC | 5hr | ||
| 13 | H | Throughput vs. (most filters) |
HRC (SBC) | 2 days |
Marks in the status column above indicate :
: Task attempted and
completed.
: Task attempted, but
either not completed, or requires further work.Campaign : Pre-TV (January/February 1999)
ACS location : GSFC clean room - dark box
Stimuli : RAS/CAL, internal lamps
Timeline : Plan ? What plan ? Basically we are doing alignment work, some noise debugs and dry running SMS's.
Campaign : Post-TV (March 1999)
ACS location : GSFC clean room - dark box
Stimuli : RAS/CAL
Timeline :
This page was written by G. Meurer. It is incomplete and to some extent, outdated.